This week we focused on revising the project requirements and updating UML diagrams accordingly. We prepared our project plan and RAM for the management of the project. We updated wiki and onboarded new team members. We decided on subteams as front-end, back-end. These subteams focused on searching the technologies they will be using. The technology selection was finalized at the end of today's lab session. Some of the requirements and product specifications were discussed with the product owner in the lab session.
- For database: PostgreSQL, Supabase
- For back-end: Django, AWS
- For hosting: GitHub Pages
- For front-end: Flutter
Subteams:
- Front-end Team: Zülal, Bengisu, Abdullah, Mehmet, Ömer Faruk, Leyla
- Back-end Team: Ömer Şükrü, Ahmed Bera, Oğuz, Hakan, Arda, Ali Mert
Our objective for the following week will be to create codebases for the project and to implement some of the basic features of the platform such as log in, sign up. We aim to revise the project plan.
Description | Issue | Assignee | Due | PR | Estimated Duration | Actual Duration |
---|---|---|---|---|---|---|
Reverify the project requirements | #240 | Team | 10.10.2023 | -- | 1hr | 3hr |
Reverify the UML diagrams if needed | #251 | Bengisu, Zülal, Leyla | 10.10.2023 | -- | 1hr | 3hr |
Update wiki pages if needed | -- | Leyla | 10.10.2023 | -- | 1hr | 10min |
Decide on what technologies are going to be used for the front-end | #249 | Front-end team | 10.10.2023 | -- | 1.5hr | 1.5hr |
Decide on what technologies are going to be used for the back-end | #248 | Back-end team | 10.10.2023 | -- | 1.5hr | 2hr |
Prepare the project plan | #243 | Team | 10.10.2023 | -- | 3.5hr | 4hr |
Prepare the Responsibility Assignment Matrix (RAM) | #246 | Hakan, Mehmet, Arda, Abdullah | 10.10.2023 | -- | 2hr | 3hr |
Adding Personal Wiki Pages | #245, #237 | Bengisu, Ömer Faruk | 10.10.2023 | -- | 1hr | 30min |
Description | Issue | Assignee | Due | PR |
---|---|---|---|---|
Determining Tasks for Project Plan | #238 | Hakan, Ömer Faruk, Ömer Şükrü, Bera, Arda | 07.10.2023 | -- |
- We decided on subteams on last meeting. But we could not finalize the subteams since we were waiting a response from the instructor about the restrictions on the technologies.
- We noticed that we need to determine tasks for project plan before we start to prepare the project plan.
- Some of the tasks were completed in the lab session due to the fact that we needed to discuss with the product owner and ask some questions to complete them.
Description | Issue | Assignee | Due | Estimated Duration |
---|---|---|---|---|
Updating the requirements according to the decisions taken and discussions with the product owner | #260 | Team | 13.10.2023 | 1hr |
Updating the UML diagrams according to the updates in the requirements | #261 | Team | 17.10.2023 | 3hr |
Review of the Project Plan | #252 | Team | 12.10.2023 | 1hr |
Review of the RAM table | #262 | Team | 12.10.2023 | 1hr |
Designing file structure outlines for front-end | #254 | Front-end Team | 13.10.2023 | 2hr |
Designing file structure outlines for back-end | #263 | Back-end Team | 13.10.2023 | 2hr |
Deciding and setting up development, testing environment | #264 | Team | 13.10.2023 | 2hr |
Defining authentication mechanisms | #265 | Team | 13.10.2023 | 2hr |
Creating User Models | #255 | Back-end Team | 15.10.2023 | 5hr |
Signup Page POST API | #256 | Back-end Team | 15.10.2023 | 3hr |
Login Page POST API | #257 | Back-end Team | 15.10.2023 | 3hr |
Signup Page | #266 | Front-end Team | 17.10.2023 | 5hr |
Login Page | #267 | Front-end Team | 17.10.2023 | 5hr |
- Some of the tasks are dependent therefore we may have timing issues.
- Some of the team members are not familiar with the selected technologies. It might take more time to get familiar with the technologies and accomplish the tasks than we expected.
- Ahmed Bera Pay
- Ahmet Abdullah Susuz
- Arda Arslan
- Bengisu Kübra Takkin
- Hakan Emre Aktaş
- Leyla Yayladere
- Mehmet Süzer
- Ömer Faruk Ünal
- Ömer Şükrü Uyduran
- Zülal Molla
🏠 Home
- Hakan Emre Aktas
- Ahmed Bera Pay
- Ömer Şükrü Uyduran
- Mehmet Süzer
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Oğuz Pançuk
- Arda Arslan
- Zülal Molla
- Leyla Yayladere
- Omer Faruk Unal
- Bengisu Kübra Takkin
451 Weekly Progress Reports
- Progress Report #1 | 03.10.2023
- Progress Report #2 | 10.10.2023
- Progress Report #3 | 17.10.2023
- Progress Report #4 | 24.10.2023
- Progress Report #5 | 07.11.2023
- Progress Report #6 | 14.11.2023
- Progress Report #7 | 21.11.2023
- Progress Report #8 | 05.12.2023
- Progress Report #9 | 12.12.2023
- Progress Report #10 | 19.12.2023
352 Meeting Notes
- Meeting #1 | 08.03.2023
- Meeting #2 | 13.03.2023
- Meeting #3 | 15.03.2023
- Meeting #4 | 22.03.2023
- Meeting #5 | 24.03.2023
- Meeting #6 | 30.03.2023
- Meeting #7 | 05.04.2023
- Meeting #8 | 07.04.2023
- Meeting #9 | 19.04.2023
- Meeting #10 | 27.04.2023
- Meeting #11 | 03.05.2023
- Meeting #12 | 06.05.2023
- Meeting #13 | 08.05.2023
- Meeting #14 | 10.05.2023
- CmpE451 Customer Milestone 1 Report
- CmpE451 Customer Milestone 2 Report
- CmpE451 Final Milestone Report