Sync examples - ITC, PTC, S-DAC
Browse files Browse the repository at this point in the history
  • Loading branch information
softwareengineerprogrammer committed Apr 15, 2024
1 parent ddbb99d commit 418cd9b
Show file tree
Hide file tree
Showing 4 changed files with 177 additions and 1 deletion.
4 changes: 3 additions & 1 deletion geophires/examples/S-DAC-GT.txt
Original file line number Diff line number Diff line change
Expand Up @@ -5,7 +5,9 @@ Based on Example 3 description: This example problem considers an EGS reservoir
The heat is used in a combined heat and power topping cycle model with double flash as
topping cycle and electricity considered as the main product.

But only lists those patameters that are different than their default values
But only lists those parameters that are different than their default values

Do S-DAC-GT Calculations, True

***Subsurface technical parameters***
*************************************
Expand Down
84 changes: 84 additions & 0 deletions geophires/examples/example_ITC.txt
Original file line number Diff line number Diff line change
@@ -0,0 +1,84 @@
--- GEOPHIRES v3 Input File
--- Created on 2024-04-12
--- Investment Tax Credit (ITC) Example

***Subsurface technical parameters***
*************************************
Reservoir Model,1, ---Multiple Fractures reservoir model
Reservoir Depth,5, ---[km]
Number of Segments,1, ---[-]
Gradient 1,55, ---[deg.C/km]
Maximum Temperature,500, ---[deg.C]
Number of Production Wells,2, ---[-]
Number of Injection Wells,2, ---[-]
Production Well Diameter,7, ---[inch]
Injection Well Diameter,7, ---[inch]
Ramey Production Wellbore Model,1, ---0 if disabled 1 if enabled
Production Wellbore Temperature Drop,.5, ---[deg.C]
Injection Wellbore Temperature Gain,0, ---[deg.C]
Production Flow Rate per Well,55, ---[kg/s]
Fracture Shape,3, ---[-] Should be 1 2 3 or 4. See manual for details
Fracture Height,900, ---[m]
Reservoir Volume Option,3, ---[-] Should be 1 2 3 or 4. See manual for details
Number of Fractures,20, ---[-]
Reservoir Volume,1000000000, ---[m^3]
Water Loss Fraction,.02, ---[-]
Productivity Index,5, ---[kg/s/bar]
Injectivity Index,5, ---[kg/s/bar]
Injection Temperature,50, ---[deg.C]
Maximum Drawdown,1, ---[-] no redrilling considered
Reservoir Heat Capacity,1000, ---[J/kg/K]
Reservoir Density,2700, ---[kg/m^3]
Reservoir Thermal Conductivity,2.7, ---[W/m/K]

***SURFACE TECHNICAL PARAMETERS***
**********************************
End-Use Option,1, ---[-] Electricity
Power Plant Type,2, ---[-] Supercritical ORC
Circulation Pump Efficiency,.8, ---[-] between .1 and 1
Utilization Factor,.9, ---[-] between .1 and 1
Surface Temperature,20, ---[deg.C]
Ambient Temperature,20, ---[deg.C]

***CAPITAL AND O&M COST PARAMETERS***
*************************************
Well Drilling and Completion Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Well Drilling Cost Correlation,1, ---[-] Use built-in correlations
Reservoir Stimulation Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Surface Plant Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Field Gathering System Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Exploration Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Wellfield O&M Cost Adjustment Factor,1, ---[-] Use built-in correlations
Surface Plant O&M Cost Adjustment Factor,1, ---[-] Use built-in correlations
Water Cost Adjustment Factor,1, ---[-] Use built-in correlations


*** Economic/Financial Parameters ***
*************************************
Plant Lifetime,30, --- [years]
Economic Model,3, --- Should be 1 (FCR model) 2 (Standard LCOE/LCOH model) or 3 (Bicycle model).
Fraction of Investment in Bonds,0.65, --- [-] Required if Bicycle model is selected. See manual for details.
Inflated Bond Interest Rate,0.07, --- [-] Required if Bicycle model is selected. See manual for details.
Inflated Equity Interest Rate,0.12, --- [-] Required if Bicycle model is selected. See manual for details.
Inflation Rate,0.025, --- [-] Required if Bicycle model is selected. See manual for details.
Combined Income Tax Rate,0.392, --- [-] Required if Bicycle model is selected. See manual for details.
Gross Revenue Tax Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Investment Tax Credit Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Property Tax Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Inflation Rate During Construction,0, --- [-]
Well Drilling and Completion Capital Cost Adjustment Factor,1, --- [-] Use built-in well cost correlation as is
Well Drilling Cost Correlation,1, --- [-] Use built-in well drilling cost correlation #1
Reservoir Stimulation Capital Cost,0, --- [M$/injection well] Reservoir stimulation capital cost per injection well
Surface Plant Capital Cost Adjustment Factor,1, --- [-] Use built-in surface plant cost correlation as is
Field Gathering System Capital Cost Adjustment Factor,1, --- [-] Use built-in pipeline distribution cost correlation as is
Exploration Capital Cost Adjustment Factor,1, --- [-] Use built-in exploration cost correlation as is
Wellfield O&M Cost Adjustment Factor,1, --- [-] Use built-in wellfield O&M cost correlation as is
Water Cost Adjustment Factor,1, --- [-] Use built-in water cost correlation as is
Surface Plant O&M Cost Adjustment Factor,1, --- [-] Use built-in surface plant O&M cost correlation as is
Investment Tax Credit Rate,0.5, --- [-] Investment tax credit rate

***Simulation Parameters***
***************************

Print Output to Console,1, ---[-] Should be 0 (don't print results) or 1 (print results)
Time steps per year,6, ---[1/year]
88 changes: 88 additions & 0 deletions geophires/examples/example_PTC.txt
Original file line number Diff line number Diff line change
@@ -0,0 +1,88 @@
--- GEOPHIRES v3 Input File
--- Created on 2024-04-12
--- Production Tax Credit (PTC) Example

***Subsurface technical parameters***
*************************************
Reservoir Model,1, ---Multiple Fractures reservoir model
Reservoir Depth,5, ---[km]
Number of Segments,1, ---[-]
Gradient 1,55, ---[deg.C/km]
Maximum Temperature,500, ---[deg.C]
Number of Production Wells,2, ---[-]
Number of Injection Wells,2, ---[-]
Production Well Diameter,7, ---[inch]
Injection Well Diameter,7, ---[inch]
Ramey Production Wellbore Model,1, ---0 if disabled 1 if enabled
Production Wellbore Temperature Drop,.5, ---[deg.C]
Injection Wellbore Temperature Gain,0, ---[deg.C]
Production Flow Rate per Well,55, ---[kg/s]
Fracture Shape,3, ---[-] Should be 1 2 3 or 4. See manual for details
Fracture Height,900, ---[m]
Reservoir Volume Option,3, ---[-] Should be 1 2 3 or 4. See manual for details
Number of Fractures,20, ---[-]
Reservoir Volume,1000000000, ---[m^3]
Water Loss Fraction,.02, ---[-]
Productivity Index,5, ---[kg/s/bar]
Injectivity Index,5, ---[kg/s/bar]
Injection Temperature,50, ---[deg.C]
Maximum Drawdown,1, ---[-] no redrilling considered
Reservoir Heat Capacity,1000, ---[J/kg/K]
Reservoir Density,2700, ---[kg/m^3]
Reservoir Thermal Conductivity,2.7, ---[W/m/K]

***SURFACE TECHNICAL PARAMETERS***
**********************************
End-Use Option,1, ---[-] Electricity
Power Plant Type,2, ---[-] Supercritical ORC
Circulation Pump Efficiency,.8, ---[-] between .1 and 1
Utilization Factor,.9, ---[-] between .1 and 1
Surface Temperature,20, ---[deg.C]
Ambient Temperature,20, ---[deg.C]

***CAPITAL AND O&M COST PARAMETERS***
*************************************
Well Drilling and Completion Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Well Drilling Cost Correlation,1, ---[-] Use built-in correlations
Reservoir Stimulation Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Surface Plant Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Field Gathering System Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Exploration Capital Cost Adjustment Factor,1, ---[-] Use built-in correlations
Wellfield O&M Cost Adjustment Factor,1, ---[-] Use built-in correlations
Surface Plant O&M Cost Adjustment Factor,1, ---[-] Use built-in correlations
Water Cost Adjustment Factor,1, ---[-] Use built-in correlations


*** Economic/Financial Parameters ***
*************************************
Plant Lifetime,30, --- [years]
Economic Model,3, --- Should be 1 (FCR model) 2 (Standard LCOE/LCOH model) or 3 (Bicycle model).
Fraction of Investment in Bonds,0.65, --- [-] Required if Bicycle model is selected. See manual for details.
Inflated Bond Interest Rate,0.07, --- [-] Required if Bicycle model is selected. See manual for details.
Inflated Equity Interest Rate,0.12, --- [-] Required if Bicycle model is selected. See manual for details.
Inflation Rate,0.025, --- [-] Required if Bicycle model is selected. See manual for details.
Combined Income Tax Rate,0.392, --- [-] Required if Bicycle model is selected. See manual for details.
Gross Revenue Tax Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Investment Tax Credit Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Property Tax Rate,0, --- [-] Required if Bicycle model is selected. See manual for details.
Inflation Rate During Construction,0, --- [-]
Well Drilling and Completion Capital Cost Adjustment Factor,1, --- [-] Use built-in well cost correlation as is
Well Drilling Cost Correlation,1, --- [-] Use built-in well drilling cost correlation #1
Reservoir Stimulation Capital Cost,0, --- [M$/injection well] Reservoir stimulation capital cost per injection well
Surface Plant Capital Cost Adjustment Factor,1, --- [-] Use built-in surface plant cost correlation as is
Field Gathering System Capital Cost Adjustment Factor,1, --- [-] Use built-in pipeline distribution cost correlation as is
Exploration Capital Cost Adjustment Factor,1, --- [-] Use built-in exploration cost correlation as is
Wellfield O&M Cost Adjustment Factor,1, --- [-] Use built-in wellfield O&M cost correlation as is
Water Cost Adjustment Factor,1, --- [-] Use built-in water cost correlation as is
Surface Plant O&M Cost Adjustment Factor,1, --- [-] Use built-in surface plant O&M cost correlation as is
Production Tax Credit Electricity, 0.05, --- [-] Production tax credit for electricity in $/kWh
Production Tax Credit Heat, 0.05, --- [-] Production tax credit for electricity in $/kWh
Production Tax Credit Cooling, 0.05, --- [-] Production tax credit for electricity in $/kWh
Production Tax Credit Duration, 10, --- [-] Production tax credit for duration in years
Production Tax Credit Inflation Adjusted, True, --- [-] Is the Production tax credit inflation adjusted (T/F)

***Simulation Parameters***
***************************

Print Output to Console,1, ---[-] Should be 0 (don't print results) or 1 (print results)
Time steps per year,6, ---[1/year]
2 changes: 2 additions & 0 deletions geophires/geophires-ui.js
Original file line number Diff line number Diff line change
Expand Up @@ -344,6 +344,8 @@ function configureExampleSelector() {
'example_SHR-2.txt',
'S-DAC-GT.txt',
'Wanju_Yuan_Closed-Loop_Geothermal_Energy_Recovery.txt',
'example_ITC.txt',
'example_PTC.txt',
]

for (let e in exampleFiles) {
Expand Down

0 comments on commit 418cd9b

Please sign in to comment.