-
-
Notifications
You must be signed in to change notification settings - Fork 48
Criticality risk
The Criticality Risk
metric is defined as:
where:
-
$W_{C}$ is the criticality weight of (black) critical activities -
$W_{R}$ is the criticality weight of (red) high-risk activities -
$W_{Y}$ is the criticality weight of (yellow) medium-risk activities -
$W_{G}$ is the criticality weight of (green) low-risk activities -
$N_{C}$ is the number of (black) critical activities -
$N_{R}$ is the number of (red) high-risk activities -
$N_{Y}$ is the number of (yellow) medium-risk activities -
$N_{G}$ is the number of (green) low-risk activities -
$N$ is the total number activities in the project, i.e.$N_{C}+N_{R}+N_{Y}+N_{G}$
Using the default settings from the Arrow Graph Settings
window, the formula would be:
The maximum possible Criticality Risk (i.e. when all activities are critical) would be:
The minimum possible Criticality Risk (i.e. when all activities are low-risk) would be:
Using the default settings from the Arrow Graph Settings
window, the result of the above formula would be:
For more details see: